英语翻译Hello Mark,Attached is the FAI report for the enclosure
来源:学生作业帮 编辑:大师作文网作业帮 分类:英语作业 时间:2024/10/03 04:43:46
英语翻译
Hello Mark,
Attached is the FAI report for the enclosure EN00416 and EN00420 fabricated in your factory for your reference.
The sample is ok except some miner issues as below,please update your files to close these items before mass production.
1.Welding:
1.1 DSBJ point welded the enclosure cover and base,it doesn’t meet our welding requirement EN00257 Rev1,you can refer to attached EN00257 standard,please update your files to reflect our welding requirement (WI,quality control plan or PFMEA),I will close this no-conformance item once I received the updated documents.
1.2 Blow hole or pin hole defects happened at welding location,DSBJ recommend to use Argon arc welding process to instead carbon dioxide welding process to prevent this kind of problem from happen again,please also update your files to reflect this change and I will close this item once received the updated file form DSBJ.
2.Rain test:
This enclosure meet NEMA 3R outdoor standard and must do rain test 100% according NEMA 3R 250 rain test procedure,please update your files to include the rain test process and I will close this item once received this updated file from DSBJ.
3.Package:
5 layers cardboard box with pallet are recommended for this enclosure packaging.
Best regards,
Hello Mark,
Attached is the FAI report for the enclosure EN00416 and EN00420 fabricated in your factory for your reference.
The sample is ok except some miner issues as below,please update your files to close these items before mass production.
1.Welding:
1.1 DSBJ point welded the enclosure cover and base,it doesn’t meet our welding requirement EN00257 Rev1,you can refer to attached EN00257 standard,please update your files to reflect our welding requirement (WI,quality control plan or PFMEA),I will close this no-conformance item once I received the updated documents.
1.2 Blow hole or pin hole defects happened at welding location,DSBJ recommend to use Argon arc welding process to instead carbon dioxide welding process to prevent this kind of problem from happen again,please also update your files to reflect this change and I will close this item once received the updated file form DSBJ.
2.Rain test:
This enclosure meet NEMA 3R outdoor standard and must do rain test 100% according NEMA 3R 250 rain test procedure,please update your files to include the rain test process and I will close this item once received this updated file from DSBJ.
3.Package:
5 layers cardboard box with pallet are recommended for this enclosure packaging.
Best regards,
碰巧我经常处理内似的客诉报告,
Hello Mark,:马克
Attached is the FAI report for the enclosure EN00416 and EN00420 fabricated in your factory for your reference.
附件EN00416 and EN00420 是你们工厂生产的首件报告.
The sample is ok except some miner issues as below,please update your files to close these items before mass production.
样品已合格,还有一些小问题如下,请在大批量生产这些产品前完善你们的文件,并解决这些问题.
1.Welding:(焊接)
1.1 DSBJ point welded the enclosure cover and base,it doesn’t meet our welding requirement EN00257 Rev1,you can refer to attached EN00257 standard,please update your files to reflect our welding requirement (WI,quality control plan or PFMEA),I will close this no-conformance item once I received the updated documents.
DSBJ点焊接到了底座和上盖周围,不能满足我们的EN00257 Rev1的焊接要求,你们也可以查看附件EN00257的标准要求,请在你们新的文件上面显示出我们的焊接要求(工作指导书,品质控制计划,或者过程失效模式及后果分析),一旦我们收到你们最新的文件就会终止不符事项.
1.2 Blow hole or pin hole defects happened at welding location,DSBJ recommend to use Argon arc welding process to instead carbon dioxide welding process to prevent this kind of problem from happen again,please also update your files to reflect this change and I will close this item once received the updated file form DSBJ.
在焊位发生下孔或针孔不良,DSBJ 建议使用氩弧焊而不是二氧化碳焊接法,可以预防这种问题再次发生,也请在你们的文件上注明这方面的改变,我们收到新的文件后交会将会终止这些项目.
2.Rain test:淋雨试验
This enclosure meet NEMA 3R outdoor standard and must do rain test 100% according NEMA 3R 250 rain test procedure,please update your files to include the rain test process and I will close this item once received this updated file from DSBJ.
需满足NEMA 3R 户外标准,必需依据NEMA 3R 250 测试标准进行100%人工淋雨试验,请更新包括淋雨试验在内的文件,一旦收到新的文件,我们将会终止这些项目.
3.Package:(包装)
5 layers cardboard box with pallet are recommended for this enclosure packaging.
建议一个卡板上放五层纸箱.
特说明:每段结尾有句“一旦收到新的文件,我们将会终止这些项目”
其意思是说,当他们收到你们对于本缺点的改善报告后,将视此项为合格项而不再追究.
诚挚问候!
Best regards,
Hello Mark,:马克
Attached is the FAI report for the enclosure EN00416 and EN00420 fabricated in your factory for your reference.
附件EN00416 and EN00420 是你们工厂生产的首件报告.
The sample is ok except some miner issues as below,please update your files to close these items before mass production.
样品已合格,还有一些小问题如下,请在大批量生产这些产品前完善你们的文件,并解决这些问题.
1.Welding:(焊接)
1.1 DSBJ point welded the enclosure cover and base,it doesn’t meet our welding requirement EN00257 Rev1,you can refer to attached EN00257 standard,please update your files to reflect our welding requirement (WI,quality control plan or PFMEA),I will close this no-conformance item once I received the updated documents.
DSBJ点焊接到了底座和上盖周围,不能满足我们的EN00257 Rev1的焊接要求,你们也可以查看附件EN00257的标准要求,请在你们新的文件上面显示出我们的焊接要求(工作指导书,品质控制计划,或者过程失效模式及后果分析),一旦我们收到你们最新的文件就会终止不符事项.
1.2 Blow hole or pin hole defects happened at welding location,DSBJ recommend to use Argon arc welding process to instead carbon dioxide welding process to prevent this kind of problem from happen again,please also update your files to reflect this change and I will close this item once received the updated file form DSBJ.
在焊位发生下孔或针孔不良,DSBJ 建议使用氩弧焊而不是二氧化碳焊接法,可以预防这种问题再次发生,也请在你们的文件上注明这方面的改变,我们收到新的文件后交会将会终止这些项目.
2.Rain test:淋雨试验
This enclosure meet NEMA 3R outdoor standard and must do rain test 100% according NEMA 3R 250 rain test procedure,please update your files to include the rain test process and I will close this item once received this updated file from DSBJ.
需满足NEMA 3R 户外标准,必需依据NEMA 3R 250 测试标准进行100%人工淋雨试验,请更新包括淋雨试验在内的文件,一旦收到新的文件,我们将会终止这些项目.
3.Package:(包装)
5 layers cardboard box with pallet are recommended for this enclosure packaging.
建议一个卡板上放五层纸箱.
特说明:每段结尾有句“一旦收到新的文件,我们将会终止这些项目”
其意思是说,当他们收到你们对于本缺点的改善报告后,将视此项为合格项而不再追究.
诚挚问候!
Best regards,
英语翻译Hello Mark,Attached is the FAI report for the enclosure
Here attached is the report for your reference.
英语翻译INDEXQUANCHAICHAPTER 1DESCRIPTIONTools for the enclosure
英语翻译Attached is the police report and the respond we got fro
英语翻译Please find attached the test report for this PO.Your pr
英语翻译Hello,overseas fans?The attached file is the final list
英语翻译the diodes used for the comparison is attached to the ph
英语翻译The enclosure is a metallic structure that has as purpos
英语翻译the attached are the wonderful photos与the attached is th
英语翻译The weatherman is giving the weather report for the week
英语翻译1.This offer is valid only for seven days.2.For the mark
Attached is the rating label for your translation